Shoe rack
Bench-Integrated Shoe Rack
DIY blueprint for Bench-Integrated Shoe Rack.
Dimensions
Width (W)
900mm
Depth (D)
350mm
Height (H)
450mm
Cut list
Tools you'll need
- ✓
Measuring Tape (5m or longer)
Used for measuring all parts.
- ✓
Pencil and Carpenter's Square
For marking lines and checking right angles.
- ✓
Saw
Home center cutting service is recommended.
- ✓
Electric Screwdriver
Using an impact driver improves work efficiency.
- ✓
Sandpaper
Prepare two types: #120 and #240.
- ✓
Level
Essential for checking horizontal alignment during assembly.
- ✓
Clamps (2 or more)
Used for temporary fixing during jointing.
- ✓
Brush and Paint Tray
Used for oil and varnish finishing.
Materials
Build steps
- 1
Measurement and Installation Location Check
≈ 15 minMeasure the installation space for the bench-integrated shoe rack (900×350×450mm). Confirm the width of the entrance area, minimum clearance for passage (600mm or more), and door swing range.
MeasureW 900 mmMeasureSTEP 1 / 13Tip
- Arrange so it does not fall within the fan-shaped range when the entrance door is opened.
- Leave at least 20mm gap between wall and furniture for easier cleaning.
- Avoid the boundary between entrance tile and flooring boards to prevent wobbling.
Watch out
- If entrance space is insufficient for 900mm width, installation is impossible. Prior measurement is essential.
- Entrance is a high-traffic area; protruding placement at foot level is a tripping hazard.
- 2
Creating the Cutting List for Parts
≈ 30 minCut 19mm thick cedar boards into front and rear boards (19×120×900mm) ×8 pieces, side boards (19×120×350mm) ×8 pieces. Bottom board is one piece of 12mm Lauan plywood (12×312×862mm). Corner posts are four pieces of 2x4 lumber (38×89×450mm). Using the home center paid cutting service is convenient.
CutUse the in-store cut serviceCutSTEP 2 / 13Tip
- Cedar boards vary greatly in knots and warping; select each piece individually.
- The 450mm length of corner posts includes height of front/rear boards (120×4 = 480mm) plus 20mm allowance.
- When using cutting service, you can specify grain alignment to enhance appearance.
Watch out
- Cedar board end grain absorbs water easily; apply protective materials thoroughly in later steps.
- 2x4 lumber actual size is 38×89mm; specify '38×89' when ordering cuts to avoid confusion.
- 3
Sanding All Parts
≈ 40 minSand with #120 then #240 sandpaper. Cedar is soft and prone to warping and splintering; pay attention to end grain and surfaces. Chamfer corner posts to make edges smooth and avoid shoes snagging or injury.
Sand#120SandSTEP 3 / 13Tip
- Cedar grain is coarse; sand with the grain direction to prevent splintering.
- Flatten end grain with #120 before finishing with #240; skipping causes uneven paint.
- Using an orbital sander can reduce sanding time to one-third; rental services are available.
Watch out
- Sanding generates large amounts of dust; perform in ventilated areas like balcony or garage.
- Do not paint without removing sanding dust; surface will be rough. Use air duster or damp cloth to clean.
- 4
Erecting and Temporarily Fixing Corner Posts
≈ 25 minStand four 2x4 lumber posts vertically and line them up at the four corners of the workbench. Clamp to the bench to fix temporarily and use a level to confirm vertical. Measure and set inner spacing between posts to front/back 600mm and left/right 300mm using measuring tape.
Build the frameTighten joints firmlyAssembleSTEP 4 / 13Tip
- Check vertical using level on two planes (front and side) to achieve zero deviation on both.
- Uneven surfaces like concrete or cushioned floors require placing plywood to create flat work surface.
- Align knots on all four posts facing same direction for better appearance, adjust by rotating.
Watch out
- If even one post is not vertical, front/rear or sides will be tilted after assembly.
- When measuring inner spacing, be consistent measuring inner or outer edges to avoid 5-10mm error.
- 5
Attaching Front and Rear Boards (Starting from Bottom)
≈ 40 minPlace the first cedar board horizontally at the bottom front, apply wood glue to the left and right corner posts, then fix with 65mm coarse-thread screws; two screws per side (total four). Stack the following boards with 5mm ventilation slits (one chopstick width) between each. Out of 10 boards total, 5 are for the front and 5 for the rear.
Build the frameTighten joints firmlyAssembleSTEP 5 / 13Tip
- 5mm ventilation slits prevent moisture buildup in shoes; tightly fitting causes mold.
- Use chopsticks to maintain even gaps.
- Drill φ4mm pilot holes on corner post side before driving screws to prevent splitting.
Watch out
- Driving 65mm screws without pilot holes can split the cedar boards; always pre-drill.
- Overdriven screws cause indentations; countersink flush with surface.
- 6
Attaching Side Boards (Left and Right)
≈ 35 minAttach eight side boards (19×120×350mm) eight in total, five each side, similarly with ventilation slits between. Before fixing side boards, adjust the front and rear boards to meet tightly at corners, ensuring edges meet. Measure diagonal length (front to back) with tape and adjust so both diagonals are equal while fixing.
Build the frameTighten joints firmlyAssembleSTEP 6 / 13Tip
- Unequal diagonal lengths cause parallelogram distortion; correct with clamps until equal.
- Side boards are inset inside front/rear boards; offset pilot hole positions slightly inward from front/rear board ends.
- If corner fitting is problematic, pre-cut corner wood at 45° miter and fasten for better finish.
Watch out
- Not aligning ventilation slits with front/rear boards results in inconsistent appearance.
- Diagonal length difference over 5mm interferes with smooth item storage.
- 7
Processing and Attaching Bottom Board
≈ 25 minDrill nine φ20mm ventilation holes (3 vertical × 3 horizontal) evenly on the 12mm Lauan plywood bottom board (312×862mm). Holes must be at least 50mm from edges and at least 100mm apart. Insert the bottom board into the box bottom and secure with 45mm coarse-thread screws to the four corner posts.
Drill a holeφ20mmDrillSTEP 7 / 13Tip
- Ventilation holes are vital for shoe moisture escape; do not reduce number.
- Use hole saw for neat holes; wood drill bit is acceptable.
- No tape needed on bottom board edges as it's not visible from outside.
Watch out
- Warped bottom boards won't fit tightly against posts; verify flatness beforehand, if warped flip and fix screws to correct.
- Placing holes too close (<50mm) to edges reduces strength.
- 8
Final Verification of Right Angles and Diagonals
≈ 15 minCheck the assembled box's right angles and diagonal lengths. Use a carpenter's square to measure four inner angles and check deviation from 90°. Measure both diagonal lengths with tape and confirm difference is within 2mm. If off, loosen screws, straighten with clamps, and retighten.
InspectNo wobble ✓InspectSTEP 8 / 13Tip
- Difference in diagonal length indicates assembly accuracy; within 2mm is acceptable for practical use.
- Measurement should be on flat and level surface for accuracy.
- Check for any loose screws by finger touch.
Watch out
- Ignoring distortions causes doors or lids to malfunction smoothly.
- Loose screws risk wobbling or structural failure under shoe load.
- 9
Painting Preparation and Sanding
≈ 15 minLightly sand entire surface with #240 sandpaper before painting and wipe off dust with damp cloth. Level areas around screw heads and end grain. Watco Oil or Briwax are suitable for indoor use.
Sand#240SandSTEP 9 / 13Tip
- Cedar absorbs paint heavily; two coats are standard.
- Apply more paint on end grain; cut surfaces have exposed fibers absorbing easily.
- Apply Watco Oil by rubbing with cloth for even finish rather than brushing.
Watch out
- Rough sanding leads to paint unevenness and fuzziness.
- Applying paint without dust removal results in rough surface.
- 10
First Coat Painting
≈ 30 minApply Watco Oil or water-based paint evenly over all surfaces. Brush or wipe along wood grain in one direction, let soak for 15-20 minutes, then wipe off excess with dry cloth. Paint ventilation slits diagonally to avoid missed areas. Let dry naturally for 2 hours or more.
PaintWatco oil / varnishPaintSTEP 10 / 13Tip
- Watco Oil 'apply and wipe off' method enhances wood texture.
- Paint pooling in ventilation slits delays drying; wipe thoroughly.
- If painting indoors, ensure good ventilation to reduce volatile fumes.
Watch out
- Forgetting to wipe excess leaves sticky surface for days; always wipe with dry cloth.
- Thick coats cause uneven drying and peeling later; always apply two thin coats.
- 11
Intermediate Sanding and Second Coat Painting
≈ 25 minAfter first coat dries, lightly sand surface with #320 sandpaper (intermediate sanding). Remove dust then apply second coat thinner than first, wiping off extra paint likewise. Allow 24 hours for full curing.
PaintWatco oil / varnishPaintSTEP 11 / 13Tip
- Intermediate sanding gently removes fuzz without removing paint film.
- Two coats greatly increase wood protection; do not skip second coat.
- Place item in dust-free area while drying.
Watch out
- Over-sanding removes first coat paint film.
- Skipping second coat halves protection; especially important for moist entrance areas.
- 12
Leg Pads and Waterproof Measures
≈ 15 minAttach felt pads or non-slip rubber pads to the bottom ends of corner posts. Rubber pads with water repellency are recommended for wet entrance areas. Silicone pads are recommended for tile floors to prevent slipping.
Fix to the wallAnchor to studsInstallSTEP 12 / 13Tip
- Felt pads absorb moisture and soil; rubber/silicone preferred for entrance.
- Pads must be attached to all four corner posts; skipping center causes tilt.
- After installation, ventilate the room for one week to dissipate paint fumes.
Watch out
- No pads cause floor scratches and slipping on wet floors.
- Some silicone pads have weak adhesion; use strong double-sided tape for security.
- 13
Final Check and Shoe Storage
≈ 15 minConfirm all screws are tight, ventilation slits are consistent, and paint finish is uniform. Use level to check for wobbling; adjust pad thickness to correct level if needed. Avoid placing heavy items long-term until paint fully cures (one week). Store shoes dry.
Done!Done — nice work!DoneSTEP 13 / 13Tip
- Wet shoes should be sufficiently dried on entrance mats before storing to prevent moisture buildup.
- Ideal shoe storage is about 80% of capacity; overfilling restricts ventilation.
- Ventilate monthly by removing all shoes and drying with fan for longevity.
Watch out
- Placing wet shoes before paint curing leaves shoe-shaped marks on paint.
- Overpacking causes deformation of wooden boards.
Warnings
- ⚠️Drill pilot holes before driving screws to prevent wood splitting.
Custom design
Changing the dimensions roughly scales the cut list. Get the precise calculation in the app.
Enter dimensions (mm)
Quick estimateWidth W
Depth D
Height H
Base size 900×350×450 mm
Cut list (preview)
Total board length ≈ 12.7 m · Available at: カインズ / コメリ / コーナン / DCM
Accurate materials, prices, and cuts in the app
Per-retailer pricing, purchase links, and optimal cut layouts are auto-calculated in the app.
Examples
Post examples from the app
Post photos, actual cost, and a comment from the app and they'll show up here.
Ratings
Comments5
- Miki2026/04/26

壁付けにする場合は背板を入れたほうが安心かなと思います
- Sachiko2026/04/26

棚柱に対して荷重バランスがよく考えられてますね。長年使うなら背板にも筋交い入れたいところ
- Reiko2026/04/26

ホームセンターで木材カットしてもらえばこの設計図でも作れそうでしょうか
2 more comment(s) in the app
Open in appCustomize the size in the app
Enter width, depth, and height in the app — the blueprint and material list are generated for you.
Find more blueprints in this category or store